TKDA designed three new campuses for Saint Louis County Public Works. The buildings are identical for project efficiencies, and the site layouts fit each unique campus location. The buildings include:
We designed the maintenance building roof and electrical load to accept future photovoltaic arrays to lighten the campus power load. TKDA worked with a Construction Manager at Risk (CMaR) to vet budget items and construction material procurement/lead times. To maintain the County’s construction schedule and budget, the maintenance building envelope construction was reviewed for different construction assembly methods. It was found that an entirely precast envelope was the most cost-effective and shortest lead time for construction. The precast package was finalized and released for procurement before finishing the construction documents to meet the lead time for the construction schedule.
CLIENT: St. Louis County Public Works
LOCATION: Saint Louis County, Minnesota